Comments: 3.5c - What progress do you expect to make during the NESTA funded phase of your project? - TIMETABLE

dates to be changed as per amended plan.

"The key milestones will be:

1. Finalisation of shooting script - May 2004

2. Completion of Animatics (interactive and film) - July 2004

3. Version one of interactivity design document - July 2004

4. Day one of principal photography on film - September 2004"

All remaining milestones beyond scope of NESTA involvement.